The expansion project of Da Nang International Airport

The expansion project of Da Nang International Airport
Started from 11/2015, Da Nang International Airport was designed on the total area of 40000 m2 including 2 separated departing and arriving halls, supporting centers, buildings, lines and roads. When finished, the airport will have 42 booths for registry, 20 for departing and 22 for arriving, 9 boarding gates with 4 bridges, 5 transmission lines and 2 package gathering spot.

The new building takes inspiration from the petrel wings with the smooth design and fit with the existing building.

As planned, the construction project will take 16 months. But as for now, 50% of the workload was completed. Most of the basic parts were completed and the process of setting up equipments and finishing interior and exterior coatings are taking place.

JOTON Paint is supplying our hi-grade products system for this important project:

+ For interior coatings: SP FILLER® Mastic, PROSIN® Hi-grade Primer and JOVIAL® Washable – Interior paint.

+For exterior coatings: JOTON® Mastic, JOTON® PROS anti-base primer, and JOTON® JOTIN Hi-grade exterior paints.

The airport is expected to enter service in 16 months, in time for the APEC summit in 2017.